The next step in our series of P25 System guides: in this issue, we take a look at implementing your P25 system after you have selected a vendor and specified system requirements. It’s time to get your network up and running.
This Best Practices Guide for implementing P25 systems discusses some common issues when getting a new network up and running. It addresses the sea of documentation that is required, and how to prepare work personnel for the challenges that the new communications system may bring.
This guide assumes that you have carefully examined and executed your contract with all parties involved, including your consultants and vendor. As soon as possible after the execution of the contract, it is good practice to hold a kick-off meeting with your vendor. This is a time for both sides to:
A system design review is intended to finalize as many details of the design and related project as possible. You need to invest significant time and preparation for a System Design Review. The purpose of this meeting is to lock in the design & project plan and enable the vendor internal procurement efforts – production equipment, purchasing third party devices, and signing up subcontractors.
The system design review provides a good opportunity to revisit and finalize a number of detailed information reports. The following technical documentation are examples of detailed information reports of high level information to consider as part of a SDR:
Factory Acceptance Tests are conducted to:
Factory Acceptance Tests are valuable when undergoing a major technological change.
Tests performed during FAT include:
Where technology change and/or the size of the system is limited, you may be able to save some time and money by foregoing the FAT and rely on your vendor to perform the necessary tests before shipment.
The role of system implementation is limited to:
It is not necessary to monitor all installation and commissioning activities. However, many system buyers delegate some of their own technical resources to participate, as they provide an excellent opportunity for hands-on training.
Formal progress monitoring is typically accomplished via regular communications from the vendor, usually structured meeting or conferences with formal progress reports.
This is but a brief explanation of Implementing your P25 System, the full version of this resource is available for free. Download your copy today.